Parking Lot Resurfacing Project
September 21–October 9
Through the Frontier Campaign, we’re investing in important infrastructure updates to care for our campus so it can continue to support vibrant ministry for years to come.
Our parking lot resurfacing will be completed in sections from September 21–October 9 to help minimize disruption. Please extend your grace and flexibility as we work to complete each section as quickly as possible.
What to Expect
- Sundays: All campus entrances, and the Chapel parking lot, are anticipated to be open on Sundays.
- Parking lot closures: Portions of the parking lot will be temporarily closed as work progresses. See the schedule and map below for anticipated closure dates and locations.
- Temporary entrance closures: The Medlock Crossing and 141 entrances will be closed briefly at certain points during the project. See the schedule and map below.
- Entrances remain open: The Old Alabama and Ventana Way entrances will remain open throughout the project.
- Perimeter School parents, please watch for carline instructions from the school.

